Minutes of 62nd FFIR/BDSIM meeting on 10/29/2003

The meeting was held in a room of 425 at KEK, 10:00-10:40, 10/29/2003. We discussed on the LC advanced R&D for the construction ready.

(1)Discussion on the LC advanced R&D

Upon request of the KEK director Totsuka, we have discussed on items,cost and manpower for the LC advanced R&D in order to be ready for the construction. At this subgroup, the R&Ds of beam delivery system were summarized. Major items are listed below; R&D of conventional final Q-magnet may be included in the final focus test facility, where many instrumentation R&D for nanometer stabilization are also included.

Costs and manpower have been estimated for each item based on experiences. Total cost is about 600,000,000 yen without facilities. Total manpower is about 40 staffs. Cost of the facilities would be same as the total cost. These estimations should be generic for LC at TeV, and they must be shared internationally.

The next meeting will be on 29th October, 2003,10:00 -noon at 3 gokan, 425 .